The Hari Hotel, Wanchai, Hong Kong
- Client: Paul Y Builders Limited
- Value: HK$468 million / US$60 million
About this Project
CDC were engaged to assist with the strengthening and pursuit of EoT claims on the project. The submitted EOT claims were reviewed and an updated assessment of the critical path was prepared following completion of the works. Additional evidence was collated and consolidated documents were prepared for submission to the architect. The revised submissions enabled negotiation of a resolution to the final account.

The Hari Hotel
More Case Studies
Power Transmission Platform, Hinkley Point C
CDC advised the contractor on a claim for delayed access to the Works and prepared a presentation in support of negotiations.
I-405 Improvement, Orange County, California
CDC undertook an independent review of expected claim revenue on the project. This involved reviewing claim documentation and cost information and verifying the estimated recovery in line with the contract terms.
Oceana Naval Air Station Runway and Lighting Repairs
CDC undertook a review of expected claim revenue on the project. This involved reviewing claim documentation, cost information, expert reports and DRB submissions and verifying the estimated recovery in line with the contract terms.