The project is being undertaken on an Engineering Procurement Construction contract. CDC prepared a claim for the main design team joint venture (SNC-Lavalin AECOM Consultants) on the project.
Case Studies
French International School
CDC were appointed by the contractor to prepare a counterclaim in relation to issues arising during the project period and reviewing the client’s counter claim for alleged defects.
Multipurpose Building in Remaining Midfield Area
CDC was engaged to review and strengthen the Contractor’s EoT entitlement documents which included ground conditions issues, COVID and changes to design intent.
Advanced Manufacturing Centre
CDC were appointed to review, research and strengthen EOT claim particulars on the building construction and the associated seawater district cooling system, prepare presentations and provide contractual advice.
Central Kowloon Route – Kai Tak West
CDC prepared claims in relation to delays to the construction of the main access shaft to the works in Ma Tau Kok and to review issues on disposal of spoil.
The Hari Hotel, Wanchai, Hong Kong
CDC were engaged to assist with the strengthening and pursuit of EoT claims on the project. The submitted EOT claims were reviewed and an updated assessment of the critical path was prepared following completion of the works.
Power Transmission Platform, Hinkley Point C
CDC advised the contractor on a claim for delayed access to the Works and prepared a presentation in support of negotiations.
I-405 Improvement, Orange County, California
CDC undertook an independent review of expected claim revenue on the project. This involved reviewing claim documentation and cost information and verifying the estimated recovery in line with the contract terms.
Oceana Naval Air Station Runway and Lighting Repairs
CDC undertook a review of expected claim revenue on the project. This involved reviewing claim documentation, cost information, expert reports and DRB submissions and verifying the estimated recovery in line with the contract terms.
Trillium Line Extension
CDC were appointed by the design team to prepare a claim for late design approvals and client impacts to the design process.
Fullerton Hotel, Ocean Park, Hong Kong
CDC provided EOT claims preparation, contract advice and negotiation support to the contractor throughout the project construction. CDC also presented issues to the Client and architect to negotiate the EoT assessments during the course of the project.
MTRC Shatin Central Link – Contract 1123, Exhibition Station and Western Approach Tunnel
CDC provided claims preparation and negotiation support to the contractor on this target cost contract, part of the Shatin to Central Link Project – North South Line. The North South Line (NSL) is a 6km extension from Hung Hom Station across the harbour to Hong Kong Island with two new stations at Exhibition and Admiralty
Hong Kong International Airport, Gate Transformation at Terminals
CDC were appointed by the Contractor to review various issues on design liability and various other contractual issues during the currency of the project.
Tuen Mun Columbarium and Garden of Remembrance
CDC was appointed to provide claims recovery and income management services to the contractor for the Tuen Mun columbarium. The columbarium will help to alleviate the acute shortage of burial space in Hong Kong by providing 160,000 niches in an eight-storey columbarium building along with a 4,800 square metre Garden of Remembrance.
East Kowloon Cultural Centre, Hong Kong
The East Kowloon Cultural Centre consists of a three-storey building housing three studios with capacities ranging between 120 and 250 seats, a 1,200-capacity auditorium, 550-seat theatre and under stage area, semi-basement areas for plant rooms, and other ancillary facilities. The project also houses a large rehearsal room, two connectable rehearsal rooms and a restaurant.
Hong Kong International Airport, Third Runway Reclamation Works
CDC was appointed to provide a contract review with regard to a subcontractor undertaking ground stabilisation to the new third runway reclamation works following termination of the subcontract.
Urban Renewal Project
CDC provided claims and delay analysis advice to the project team to strengthen the negotiation position for the project. The project comprises the construction of two towers with a total of 493 residential flats on a three-storey podium.
Gerald Desmond Bridge
CDC provided contractual advice, claims management and claims preparation to the international joint venture contractor for the project. The project comprises a high-level cable stayed bridge with two 150m tall towers supporting a 300m main span over the entrance to the Port of Long Beach California, two 500m backspans and 900m approach viaducts and will carry 15% of all goods coming into the USA.
Samuel de Champlain Bridge
CDC undertook a commercial claims review of the existing recovery strategy and advised the senior management on options to improve the Champlain Bridge project’s commercial position.
Passenger Crossing Boundary Facility Hong Kong Macau Zhuhai Bridge
The Hong Kong Macau Zhuhai Bridge project is a 55km long bridge and tunnel system across the Pearl River Estuary. The Hong Kong Passenger Crossing Boundary Facility is situated on a reclaimed island on the north coast of Lantau.