WSD Pressure Management and District Monitoring System
- Client: Gammon Construction Limited
- Value: HK$240 million / US$30 million
About this Project
The project comprised a term contract for installation of flowmeters and valves into the existing water supply network in Kowloon and Hong Kong Island. CDC provided advice to the Contractor in relation to a dispute arising from measurement issues on the contract. CDC also prepared the position paper for mediation and advised the Contractor on negotiating with the client to resolve the commercial issues. The issues were ultimately resolved through negotiation.
More Case Studies
Oceana Naval Air Station Runway and Lighting Repairs
CDC undertook a review of expected claim revenue on the project. This involved reviewing claim documentation, cost information, expert reports and DRB submissions and verifying the estimated recovery in line with the contract terms.
Trillium Line Extension
CDC were appointed by the design team to prepare a claim for late design approvals and client impacts to the design process.
Fullerton Hotel, Ocean Park, Hong Kong