Hong Kong International Airport, Third Runway Reclamation Works
- Client: T & M Specialists Limited
- Value: HK$10 million
About this Project
CDC was appointed to provide a contract review with regard to a subcontractor undertaking ground stabilisation to the new third runway reclamation works following termination of the subcontract. CDC reviewed the various issues and assisted in drafting correspondence to assist the subcontractor in pursuing its monetary claims. CDC also provided advice to the subcontractor on strategies related to dispute resolution. The issues were resolved through negotiation by the parties.
More Case Studies
Multipurpose Building in Remaining Midfield Area
CDC was engaged to review and strengthen the Contractor’s EoT entitlement documents which included ground conditions issues, COVID and changes to design intent.
Advanced Manufacturing Centre
CDC were appointed to review, research and strengthen EOT claim particulars on the building construction and the associated seawater district cooling system, prepare presentations and provide contractual advice.
Central Kowloon Route – Kai Tak West
CDC prepared claims in relation to delays to the construction of the main access shaft to the works in Ma Tau Kok and to review issues on disposal of spoil.