Time Travel for Adjudicators: What Mace v Baltic Means for NEC4 Compensation Events
Mace Construct Ltd v Baltic Investment Holdings Ltd [2026] EWHC 976 (TCC) confirms a principle that matters directly to NEC4 practitioners: a prospective method of delay assessment cannot be abandoned for a retrospective one simply because hindsight is more convenient. The case arose from a challenge to a previously granted extension of time, and the court’s reasoning applies directly to the Clause 60–65 compensation event framework.
The dispute
Baltic’s Employer’s Agent granted Mace a prospective extension of time of seven weeks and five days during the works. Baltic challenged the award in adjudication. The adjudicator reopened it and reduced it to nil. Mace then brought Part 8 proceedings, arguing that because the contract required a prospective assessment — judged without the benefit of hindsight — no adjudicator or court could meaningfully redo that exercise later, once the outcome was already known. On that logic, the original award should stand as final.
What the court decided
The TCC rejected that conclusion. Adjudicators retain the broad power to open up, revise and review earlier decisions unless the contract makes them final. Otherwise, an employer could be left “eternally saddled with an erroneous extension of time.” However, the court did not allow the adjudicator to simply substitute whatever method seemed most convenient. Instead, the adjudicator had to “stand in the shoes” of the original decision-maker and perform the same exercise the contract required — here, a prospective assessment based only on information available at the time, ignoring what actually happened afterwards.
The court accepted that this is genuinely difficult. Deliberately setting aside a known outcome, to reconstruct a judgement that should have been made earlier, goes against a reviewer’s natural instincts. However, the court treated that difficulty as a question of evidence and procedure, not a reason to change the method.
Why this matters under NEC4
NEC4’s compensation event regime is prospective by design — more explicitly so than most other standard forms of contract. Clause 63.1 values the change to the Prices by reference to actual Defined Cost up to the “dividing date” and forecast Defined Cost afterwards. The dividing date is a concept added specifically to fix which point in time governs. Clause 63.5 assesses delay against the Accepted Programme current at the dividing date, not against whatever sequence or critical path later occurred. This reflects a deliberate allocation of risk: the Contractor carries the risk of the forecast element, in exchange for a fixed figure calculated once, at a defined moment — not a running account that gets rewritten every time new information emerges.
Mace v Baltic confirms that an adjudicator reviewing a compensation event assessment cannot replace the prospective exercise NEC4 requires with a retrospective reconstruction of what “really” happened. A wrong dividing date, a misjudged Accepted Programme, or a poor forecast are all proper grounds for revision. But the revision itself must still be carried out from the same vantage point as the original assessor, using only the information available at the time.
Practical implications
- Preserve the contemporaneous record, not just the outcome. What matters on review is what was known, and what the Accepted Programme showed, at the dividing date — not as-built analysis produced after the fact.
- Anchor assessments expressly to the dividing date. A quotation or Project Manager’s assessment that clearly ties itself to the relevant point in time is far harder to dislodge than one blending contemporaneous and after-the-fact reasoning.
Conclusion
The judgment confirms that compensation event and extension of time assessments remain reviewable. But being reviewable does not mean the contract’s prescribed method can be abandoned. An adjudicator revisiting a prospective assessment must still perform a prospective one — however awkward that becomes once the actual outcome is already known. The safer approach for anyone preparing NEC4 compensation event submissions is to build the prospective case properly, on a contemporaneous footing, the first-time round.
About Contract Dispute Consultants
With offices in Hong Kong and Singapore, CDC are Asia’s leading claims and contractual consultancy providing support to first tier contractors working on complex infrastructure and building projects worldwide. We work to manage and minimise contractual risk to assist contractors in negotiating early resolution of issues before they escalate. Recent assignments have included advising contractors on NEC3 and NEC4 projects involving metro, tunnels and water works. Other assignments have included rail projects in Canada and Hong Kong, cable stayed bridges in the United States, Canada and Hong Kong, power projects in the UK and airport projects.