WSD Pressure Management and District Monitoring System

  • Client: Gammon Construction Limited 
  • Value: HK$240 million / US$30 million

About this Project

The project comprised a term contract for installation of flowmeters and valves into the existing water supply network in Kowloon and Hong Kong Island.  CDC provided advice to the Contractor in relation to a dispute arising from measurement issues on the contract. CDC also prepared the position paper for mediation and advised the Contractor on negotiating with the client to resolve the commercial issues. The issues were ultimately resolved through negotiation.  
South Island Line – 903 Ocean Park Station

More Case Studies

French International School

French International School

CDC were appointed by the contractor to prepare a counterclaim in relation to issues arising during the project period and reviewing the client’s counter claim for alleged defects.