Power Transmission Platform, Hinkley Point C
- Client: Linxon United Kingdom
- Value: GBP112 million / US$142 million
About this Project
The project includes the design, manufacture, installation and commissioning of the Power Transmission Platform comprising Step Up Power Transformers, Auxiliary Transformers, and Station Service Transformers and associated auxiliaries, cabling, gas insulated switchgear, panels and structures along with connections to the overhead grid and underground high voltage cables. The installation would service the new Hinkley Point C nuclear power station, the largest project in Europe.
CDC advised the contractor on a claim for delayed access to the Works and prepared a presentation in support of negotiations.
More Case Studies
Réseau express métropolitain (REM), Montreal, Quebec
The project is being undertaken on an Engineering Procurement Construction contract. CDC prepared a claim for the main design team joint venture (SNC-Lavalin AECOM Consultants) on the project.
French International School
CDC were appointed by the contractor to prepare a counterclaim in relation to issues arising during the project period and reviewing the client’s counter claim for alleged defects.
Multipurpose Building in Remaining Midfield Area
CDC was engaged to review and strengthen the Contractor’s EoT entitlement documents which included ground conditions issues, COVID and changes to design intent.