The Hari Hotel, Wanchai, Hong Kong

  • Client: Paul Y Builders Limited
  • Value: HK$468 million / US$60 million

About this Project

The works involved the construction of a 30-storey hotel building, with a total construction floor area of approximately 12,123 square metres consisting of restaurants, covered carpark, penthouses, plant rooms and refuge floor from ground floor to 6th floor, the guestrooms and lift lobbies from 7th to 30th floor, providing 210 guest rooms.​

CDC were engaged to assist with the strengthening and pursuit of EoT claims on the project.  The submitted EOT claims were reviewed and an updated assessment of the critical path was prepared following completion of the works. Additional evidence was collated and consolidated documents were prepared for submission to the architect. The revised submissions enabled negotiation of a resolution to the final account.

Ocean Park Water World Hong Kong

The Hari Hotel

More Case Studies

French International School

French International School

CDC were appointed by the contractor to prepare a counterclaim in relation to issues arising during the project period and reviewing the client’s counter claim for alleged defects.