CDC undertook a review of expected claim revenue on the project. This involved reviewing claim documentation, cost information, expert reports and DRB submissions and verifying the estimated recovery in line with the contract terms.
Infrastructure
Trillium Line Extension
CDC were appointed by the design team to prepare a claim for late design approvals and client impacts to the design process.
Hong Kong International Airport, Third Runway Reclamation Works
CDC was appointed to provide a contract review with regard to a subcontractor undertaking ground stabilisation to the new third runway reclamation works following termination of the subcontract.
Gerald Desmond Bridge
CDC provided contractual advice, claims management and claims preparation to the international joint venture contractor for the project. The project comprises a high-level cable stayed bridge with two 150m tall towers supporting a 300m main span over the entrance to the Port of Long Beach California, two 500m backspans and 900m approach viaducts and will carry 15% of all goods coming into the USA.
Samuel de Champlain Bridge
CDC undertook a commercial claims review of the existing recovery strategy and advised the senior management on options to improve the Champlain Bridge project’s commercial position.
Passenger Crossing Boundary Facility Hong Kong Macau Zhuhai Bridge
The Hong Kong Macau Zhuhai Bridge project is a 55km long bridge and tunnel system across the Pearl River Estuary. The Hong Kong Passenger Crossing Boundary Facility is situated on a reclaimed island on the north coast of Lantau.
Stonecutters Bridge
Stonecutters Bridge is a 1,108m main span cable-stayed bridge over the entrance to Hong Kong’s container terminal (currently the third longest in the world). CDC acted for the contractor managing the complete commercial claims function throughout the construction.
Tseung Kwan O to Lam Tin Tunnel
CDC were appointed to prepare a strategy paper to identify recovery options for time and cost on the main tunnelling and lining works for the Tseung Kwan O to Lam Tin Tunnel project.
Tolo Highway Widening
CDC provided advice to the Contractor in relation to a dispute regarding contractual interpretation for formwork finishes on the Tolo Highway widening project. CDC advised on appointment of experts, presentation of the claim as well as drafting the statement of clam for a mediation hearing.
Black Point Power Station
CDC provided claims and income management services to the civil works contractor for the Black Point Power Station Combined Cycle Gas Turbine project. The development is part of the Hong Kong government’s effort to replace older oil generation units with cleaner gas turbines to improve the territory’s air quality.
Midfield Terminal, Hong Kong International Airport
CDC provided ongoing contractual advice, claims management and preparation and led a multi-disciplinary team to resolve issues through mediation for the Midfield Terminal at Hong Kong International Airport.
MTR South Island Line Ocean Park and Wong Chuk Hang Stations
CDC prepared claims and position papers for the contractor in relation to securing increases of the target cost on this project comprising construction of two MTR stations and connecting viaducts.
MTR Express Rail Ngau Tam Mei to Tai Kong Po Tunnels
CDC provided contractual advice, claims management and preparation and negotiation support for the contractor. The project comprises 2.6km of twin tunnels constructed by drill and blast between two access shafts, one 40m deep and the other 90m deep.
MTR South Island Line Lei Tung and South Horizons Stations and Tunnels
CDC prepared claims for delay, disruption and extensions of time on the station structure and shaft excavation works for the negotiation of a supplemental agreement. The project comprised cut and cover tunnels and station structure and cavern excavation.
MTRC Express Rail Kowloon Terminus
CDC provided contractual advice, claims management and preparation and negotiation for several works packages under the JV agreement, including fabrication and erection of cruciform columns for the main station structure, provision of concrete and temporary work elements.
Kennedy Town Station
CDC provided contractual and strategic advice, claims management and claim preparation for the Kennedy Town station construction project. The project comprised construction of an underground railway station and overrun tunnel in a congested urban environment.
WSD Pressure Management and District Monitoring System
The project comprised a term contract for installation of flowmeters and valves into the existing water supply network in Kowloon and Hong Kong Island.
Ingiriya to Ratnapura Highway A8 Upgrade Sri Lanka
The project comprised the rehabilitation and improvement of 33km of road between Ingirya in Kalutara District of the Western Province and Ratnapura, the capital city of Sabaragamuwa Province.
Harbour Area Treatment Scheme Stage 2
The project comprised the construction of a 12km long sewage conveyance system from North Point Preliminary Treatment Works to Stonecutters Island Sewage Treatment Works.